Question: Example # 2 : Crashing a Project Assumptions All tasks on the project can be crashed, with the $ ? day cost listed Each activity

Example #2:
Crashing a Project
Assumptions
All tasks on the project can be crashed, with the $? day cost listed
Each activity can be crashed until there is 1 day duration left
Management has stated that every day we can end project sooner is worth $275
What is the sequence of activities to crash?
3 davs