Question: Example (EAC) Case-I: You have a project which is worth 500,000 USD. Seven months have passed and 350,000 USD has been spent. Upon closer review
Example (EAC) Case-I:
You have a project which is worth 500,000 USD. Seven months have passed and 350,000 USD has been spent. Upon closer review you find that only 60% of the work is completed; however, as per the schedule, 65% of the work should have been completed.
Determine the Estimate at Completion (EAC).
Solution:
Estimate At Completion = (Budget At Completion)/(Cost
Performance Index) EAC = BAC/CPI
And,
Cost Performance Index = (Earned
Value)/(Actual Cost) CPI = EV/AC
Earned Value = 60% of BAC
= 0.6 * 500,000
= 300,000
Actual Cost
= 350,000
Hence,
CPI = (Earned Value)/(Actual Cost)
= 300,000/350,000
= 0.86
Hence,
EAC = 500,000/0.86
= 581,395
Hence the Estimate at Completion (EAC) is 581,395 USD.
Practice Question: 11
You have recently joined an ongoing project. The cost of the project is 350,000 USD, and 150,000 USD has already been spent and 40% of the work is actually completed. However, according to the schedule, 43% of the work should have been completed to date.
Determine the EAC
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
