Question: Lab Project # 7 ( 1 5 pts . ) IS 1 8 7 / MGMT 1 5 8 S 2 0 2 0 Example

Lab Project #7(15 pts.)
IS187/ MGMT 158 S2020
Example (EAC) Case-I:
You have a project which is worth 500,000 USD. Seven months have passed and
350,000 USD has been spent. Upon closer review you find that only 60% of the work is
completed; however, as per the schedule, 65% of the work should have been completed.
Determine the Estimate at Completion (EAC).
Solution:
Estimate At Completion =(Budget At Completion)/(Cost
Performance Index) EAC = BAC/CPI
And,
Cost Performance Index =(Earned
Value)/(Actual Cost) CPI = EV/AC
Earned Value =60% of BAC
=0.6*500,000
=300,000
Actual Cost
=350,000
Hence,
CPI =(Earned Value)/(Actual Cost)
=300,000/350,000
=0.86
Hence,
EAC =500,000/0.86
=581,395
Hence the Estimate at Completion (EAC) is 581,395 USD.
2
***
Practice Question: 11
You have recently joined an ongoing project. The cost of the project is 350,000 USD,
and 150,000 USD has already been spent and 40% of the work is actually completed.
However, according to the schedule, 43% of the work should have been completed to
date.
Determine the EAC.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!