Question: Example Example 8 . 1 0 : Maintenance workload for the next five months is 2 , 5 0 0 , 1 , 5 0

Example
Example 8.10: Maintenance workload for the next five months is 2,500,1,500,1800,2800 and 2200 man-hours. This workload can be met by employees on regular time at a cost of $10 per hour, employees on overtime at a cost of $15 per Lour, or subcontractors at a cost of $18 per hour. The initial workforce size is 10 employes. Each employee works for 150 regular time hours and a maximum of 60 overtime work hours per month. Maximum capacity of subcontract workers is 200 in per month. Early maintenance costs $8 per hour per month, while late maintenance costs $14 per hour per month. For each employee, hiring cost is $800 and fring cost is $1000. Assuming zero starting and ending backlog, model and solve this capacity planning problem using mathematical programming.
 Example Example 8.10: Maintenance workload for the next five months is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To model and solve this capacity planning problem using mathematical programming follow these steps ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!