Question: Maintenance workload for the next five months i s 2 , 5 0 0 , 1 , 5 0 0 , 1 8 0 0

Maintenance workload for the next five months is2,500,1,500,
1800,2800 and 2200 man-hours. This workload can be met by employees on
regular time at a cost of $10 per hour, employees on overtime at a cost of $15 per
hour, or subcontractors at a cost of $18 per hour. The initial workforce size is10
employees. Each employee works for 150 regular time hours and a maximum of60
overtime work hours per month. Maximum capacity of subcontract workers is200
h per month. Early maintenance costs $8 per hour per month, while late
maintenance costs $14 per hour per month. For each employee, hiring cost is $800
and firing cost is $1000. Assuming zero starting and ending backlog, model and
solve this capacity planning problem using mathematical programming.
 Maintenance workload for the next five months is2,500,1,500, 1800,2800 and 2200

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!