Question: Example: Steel Erection Subtask Total U/M Allowed Credit .10 .25 .35 Total Quantity 100 250 To-Date Quantity 100 Earned Tons 150 % Delivery Columns Beams

Example: Steel Erection Subtask Total U/M Allowed Credit .10 .25 .35 Total Quantity 100 250 To-Date Quantity 100 Earned Tons 150 % Delivery Columns Beams Plumb Punchlist Steel Erection Each Each Each 100 144 100 210 250 .15 1.00 % 20 45 Total Tons 1500 Total value is $900,000 Use the chart above to answer the following questions. 1. What is the "To Date Quantity" for Delivery"? 2. What is the Earned Tons" for Columns? 3. What is the Total Quantity" of "Beams"? 4. What is the "Earned Tons" for "Plumb"? 5. If all of your activities are complete except "Punchlist", what is the dollar value of the work to be completed? Example: Steel Erection Subtask Total U/M Allowed Credit .10 .25 .35 Total Quantity 100 250 To-Date Quantity 100 Earned Tons 150 % Delivery Columns Beams Plumb Punchlist Steel Erection Each Each Each 100 144 100 210 250 .15 1.00 % 20 45 Total Tons 1500 Total value is $900,000 Use the chart above to answer the following questions. 1. What is the "To Date Quantity" for Delivery"? 2. What is the Earned Tons" for Columns? 3. What is the Total Quantity" of "Beams"? 4. What is the "Earned Tons" for "Plumb"? 5. If all of your activities are complete except "Punchlist", what is the dollar value of the work to be completed
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts