Question: Exercise 1 0 : A project activity has been determined to have the following potential durations: An optimistic completion time of 1 2 days, a
Exercise :
A project activity has been determined to have the following potential durations:
An optimistic completion time of days, a pessimistic completion time of days, and a most likely completion time of days. What is the estimated activity duration using the weighted average technique?
Exercise : Network Diagram
Construct a network diagram using the following information:
tableTask name,Predecessor,DurationANone,BNone,CADA BEBFC D E
a What is the critical path?
b What is the project duration?
c What is the float at task C
d What is the early start of task E
e What is the late finish of task A