Question: Exercise #1 - Complete the Table and Confirm Critical PATH H Task 9 END Task I Task 6 Deliverable B 0 2 2 2 4


Exercise #1 - Complete the Table and Confirm Critical PATH H Task 9 END Task I Task 6 Deliverable B 0 2 2 2 4 6 2 Start Task 2 Task 3 Deliverable A Task 7 DURATION EE 0 2 2 NAME Task 4 SLACK LE