Question: - Exercise #1 - Complete the Table and Confirm Critical PATH 0 2 2 Task 9 12012 END 6 612 044 Task 1 120 12

- Exercise #1 - Complete the Table and Confirm Critical PATH 0 2 2 Task 9 12012 END 6 612 044 Task 1 120 12 Deliverable B Task 6 0 0 0 Start 0 2 2 Task 2 2 46 Task 3 6 0 6 Deliverable A 628 Task 7 ES DURATION EE NAME SLACK LE 0 2 2 Task 4 LS - Exercise #2 - Build the Flow and Confirm Critical Path Task Duration Task Predecessors (hours) Task ID 0 Task Description Project start Buy materials for A Buy materials for B B A 10 20 D Build A 30 B, C B, C E Build B 20 F E 40 6 I G Polish and finish B Join A and B Project finish D, F 20 H G 0