Question: Exercise 2 Based on the information provided below: ( a ) Prepare AOA network ( b ) Using PDM , calculate activity information and determine

Exercise 2
Based on the information provided below:
(a) Prepare AOA network
(b) Using PDM, calculate activity information and determine critical path.
\table[[Activity,\table[[Duration],[(weeks)]],\table[[Immediate],[predecessor(s)]]],[A,5,-],[B,4,A],[C,5,A],[D,7,A],[E,6,A],[F,4,B & C],[G,3,E],[H,3,F & D],[I,6,E],[J,1,G & H],[K,4,I & J]]
Note: For all activities, assume FS dependency with no lag.
36
Exercise 2 Based on the information provided

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!