Question: Exercise 2: Excel: Ch5_Solved Problems ACTIVITY TIME (DAYS) IMMEDIATE PREDECESSORS A 1 - B 4 A 3 A D 7 A E 6 B F

Exercise 2: Excel: Ch5_Solved Problems ACTIVITY

Exercise 2: Excel: Ch5_Solved Problems ACTIVITY TIME (DAYS) IMMEDIATE PREDECESSORS A 1 - B 4 A 3 A D 7 A E 6 B F 2 2 C, D G 7 E, F H 9 D I 4 G H 1. Draw the critical path diagram. 2. Show the early start, early finish, late start, and late finish times. 3. Show the critical path. 4. What would happen if activity F was revised to take four days instead of two