Question: Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time (days) Immediate Predecessor(s) A
Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time (days) Immediate Predecessor(s) A 1 B 4 A C 5 A D 3 B E 1 B F 6 B, C G 2 D, E H 6 F I 5 F J 8 G, H, I