Question: Exercise 2: Given the following project plan Activity Predecessor Duration Cost/Day Total (days) cost A 3 400 1200 B A 4 500 2000 | B

Exercise 2: Given the following project plan Activity Predecessor Duration Cost/Day Total (days) cost A 3 400 1200 B A 4 500 2000 | B 4 500 2000 D B 3 300 900 E D 4 200 800 Where all the cies assumed to be FS-Finish to Start. And Consider the following field report at the end of day 10 Activity | A B Field report at the end of day 10 Actual % Incurred Cost complete 100 1200 100 2400 25 600 33 300 0 0 | D E Perform an analysis of the project status at the end of day 10, using EVA. Use CPI and SPI to determine project efficiency Exercise 2: Given the following project plan Activity Predecessor Duration Cost/Day Total (days) cost A 3 400 1200 B A 4 500 2000 | B 4 500 2000 D B 3 300 900 E D 4 200 800 Where all the cies assumed to be FS-Finish to Start. And Consider the following field report at the end of day 10 Activity | A B Field report at the end of day 10 Actual % Incurred Cost complete 100 1200 100 2400 25 600 33 300 0 0 | D E Perform an analysis of the project status at the end of day 10, using EVA. Use CPI and SPI to determine project efficiency
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
