Question: Exercise 3 Below are the project costs estimates using a top-down approach. The costs of each top project deliverables for each phase are apportioned as
Exercise 3
Below are the project costs estimates using a top-down approach. The costs of each top project deliverables for each phase are apportioned as a percentage of the total project cost.
Total Project Costs: $550,000
Planning Phase:
Planning Cost: 15%
Design Cost: 20%
Execution Phase:
Engineering Cost: 25%
Engineering Material Cost: 10%
Implementation Phase:
Test Cost: 20%
Documentation Cost: 10%
- What are the total project costs for each phase?
- What weaknesses are inherent in this estimating approach?