Question: Exercise 4 . 1 3 A business process experiences a market demand of 3 5 jobs per day. A working day consists of 4 9
Exercise
A business process experiences a market demand of jobs per day. A working day consists of minutes, and the process activity times do not exhibit significant amounts of variation. A process management team would like to apply the linebalancing technique to assign activities to workstations. The activity times and the immediate predecessors to each activity are given in Table
a Use the longest activity time rule as the primary rule to assign activities to stations.
b Compute the efficiency of the line to the theoretical maximum efficiency. Is it possible to improve the line efficiency?
TABLE
Data for Exercise
tableActivityTime minImmediate PredecessorABCADA BE