Question: Exercise #9: Review the following network ( this is the same network from Exercise #8) and the estimated activity times in the chart below: _A

  • Exercise #9:
    • Review the following network (this is the same network from Exercise #8) and the estimated activity times in the chart below:

  • _Activity_ _____a____ ____m____ ____b____
    A 6.5 7.5 14.5
    B 8.5 10.5 12.5
    C 2.5 3.5 4.5
    D 6.5 7.5 8.5
    E 5.5 5.5 9.5
    F 5.5 7.5 9.5
    G 4.5 6.5 8.5
    H 2.5 3.5 3.5

  • For Exercise #9, assemble a table showing the Expected Duration, and Variance of each activity, then calculate the probability the project will finish in 25, 27, and 30 days (Note: this is different than the directions given in the textbook).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!