Question: Exercise #9: Review the following network ( this is the same network from Exercise #8) and the estimated activity times in the chart below: _A
- Exercise #9:
- Review the following network (this is the same network from Exercise #8) and the estimated activity times in the chart below:
-
_Activity_ _____a____ ____m____ ____b____ A 6.5 7.5 14.5 B 8.5 10.5 12.5 C 2.5 3.5 4.5 D 6.5 7.5 8.5 E 5.5 5.5 9.5 F 5.5 7.5 9.5 G 4.5 6.5 8.5 H 2.5 3.5 3.5
- For Exercise #9, assemble a table showing the Expected Duration, and Variance of each activity, then calculate the probability the project will finish in 25, 27, and 30 days (Note: this is different than the directions given in the textbook).