Question: Exercise: Performance Measurement A - 1 2 Avenger II Program Background Replacement for the US Navy s A - 6 Intruder aircraft January 1 9

Exercise: Performance Measurement
A-12 Avenger II Program
Background
Replacement for the US Navys A-6 Intruder aircraft
January 1988, General Dynamics and McDonnell Douglas were
awarded the full-scale development program
Contract
6 year fixed price incentive contracts
5 full-scale test articles; 8 flight units
First flight schedule for June 17,1990
What Happened
December 1989 formal program review
Navy Program Manager declared program on schedule, on cost, on track
Cost Performance Data provided starting in February 1989
Data for April 1990, Millions of Dollars
Activities PV EV AC CV CPI TCPI SV SPI BAC EAC VAC
A-12 $2,080 $1,491 $1,950($459)0.7651.043($589)0.717 $ 4,046 $ 4,400($354)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!