Question: Exercise Question: Costs for a project are $12,000 per week for as long as the project lasts. The project manager has supplied the cost and

Exercise Question: Costs for a project are
Exercise Question: Costs for a project are $12,000 per week for as long as the project lasts. The project manager has supplied the cost and time information shown. Use the information to: Determine an optimum crashing plan. Summarize the total costs for the plan. a) b) 14 weeks 10 weeks a b Activity Crashing Potential (weeks) 3 3 13 weeks 6 weeks d a 15 weeks b Cost per Week to Crash $11,000 3,000 first week, $4,000 others 6,000 1,000 6,000 2,000 e 8 weeks d 2 1 3 1 e f