Question: EXHIBIT 2 : ENTERPRISE RESOURCE PLANNING PROJECT PLAN WITH TASKS AND MILESTONES Milestone 1 ( Transfer data from QB ) New coding system for the

EXHIBIT 2: ENTERPRISE RESOURCE PLANNING PROJECT PLAN WITH TASKS AND
MILESTONES
Milestone 1(Transfer data from QB)
New coding system for the products and parts (2 weeks)
Formal training for the employees (4 weeks)
Bill of materials module (4 weeks, 1FS)
Inventory management module (4 weeks, 1FS)
Milestone 2(Customer-side implementation complete)
Develop quoting communication application (8 weeks, 4 FS )
Estimation and quoting module (8 weeks, 4 FS )
Engineering module (8 weeks, 4 FS )
Sales module (8 weeks, 4 FS )
CRM module (6 weeks, 8SS+2 weeks)
Shipping module (5 weeks, 8SS+3 weeks)
Milestone 3(Supplier-side implementation complete)
Purchasing module (6 weeks, 4FS)
Receiving module (6 weeks, 4FS)
Milestone 4(Go live, end of parallel run of the legacy system)
Accounting module (6 weeks, 12SS+1 week)
Milestone 5(Start of automated regular transfer of bookkeeping data from ERP to QB)
Develop the ERP-to-QB transfer application (3 weeks, 13FS)
Milestone 6(Production-side implementation complete):
MRP module (3 weeks, 4FS)
Start using work orders (9 weeks, 15FS)
Scheduling module (9 weeks, 16SS+3 weeks)
Shop floor control module (2 weeks, 16FS)
Quality management module (6 weeks, 18FS)
Preventive maintenance module (4 weeks, 18FS)
Milestone 7(End project):
Develop customer status reporting application (4 weeks, 19FS,20FS) LOOKING AT THE CASE STUDY DISCUSS ON BROADBAND-X: ENTERPRISE RESOURCE PLANNING IMPLEMENTATION. IVEY Publishing, Kindly
1. Discuss the motives that drove Broadband-X to implement an ERP software
2. Do you think Broadband-X should have bought a custom-built ERP software rather than an off-the-shelf ERP software? Give reasons for your answer
3. Evaluate the biggest challenges and risks Broadband-Xwill face during the ERP implementation, and suggest strategies for mitigating these risks .
4.Develop an ERP implementation project plan most fitting to Broadband-X's situation, accompanied by an implementation strategy (communication, project roles, training, etc.)-Use this question to develop your project planning skills. Use the data in the Project Plan section and in Exhibit 2. As part of your answer, a Gantt chart created using Microsoft Project is required. Copy and paste your Gantt chart into the document you are submitting
 EXHIBIT 2: ENTERPRISE RESOURCE PLANNING PROJECT PLAN WITH TASKS AND MILESTONES

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!