Question: Exhibit 4 . 1 3 : Work Breakdown Structure and Activities for the Cell Phone Design Project table [ [ MAJOR SUBPROJECTS / ACTIVITIES

Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
\table[[MAJOR SUBPROJECTS/ACTIVITIES,ACTIVITY IDENTIFICATION,DEPENDENCY,DURATION (WEEKS)],[Product Specifications (P)],[Market research,P1,-,6],[Overall product specifications,P2,P1,6],[Hardware,P3,P2,6],[Software,P4,P3,6],[Supplier specifications (S)],[Hardware,S1,P4,5],[Software,S2,P4,6],[Product design (D)],[Battery,D1,S1,1],[Display,D2,S1,2],[Camera,D3,S1,1],[Outer cover,D4,D1, D2, D3,4],[Product integration (I)],[Hardware,I1,D4,3],[User interface,I2,D2,4],[Software coding,I3,I2,3],[Prototype testing,I4,I1, I3,5],[Subcontracting (V)],[Suppliers selection,V1,S1, S2,10],[Contract negotiation,V2,I4, V1,4]] a. Calculate the start and finish times for each activity. (Leave no cells blank - be certain to enter "0" wherever required.) b. Determine the minimum number of weeks for completing the project.
Minimum number of weeks
c. Find the activities that are on the critical path for completing the project in the shortest time.
P1-P2-P3-P4-S1-D2-D4-I1-I4-V2
P1-P2-P3-P4-S1-D1-D4-11-I4-V2
P1-P2-P3-P4-S1-D2-I2-I3-I4-V2
P1-P2-P3-P4-S1-D3-D4-I1-I4-V2 You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject P involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject S supplier specifications. These involve engineering details for how the product will perform.
The individual components that make up the product are the focus of subproject D. Subproject I brings all the components together, and a working prototype is built and tested.
Finally, in subproject V, suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)
Market research P16
Overall product specifications P2 P16
Hardware P3 P26
Software P4 P36
Supplier specifications (S)
Hardware S1 P45
Software S2 P46
Product design (D)
Battery D1 S11
Display D2 S12
Camera D3 S11
Outer cover D4 D1, D2, D34
Product integration (I)
Hardware I1 D43
User interface I2 D24
Software coding I3 I23
Prototype testing I4 I1, I35
Subcontracting (V)
Suppliers selection V1 S1,S210
Contract negotiation V2 I4, V14
 Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!