Question: Exhibit one presents a partial MRP transaction report for the parts and necessary to manufacture the lamp shown in the product structure to the right

Exhibit one presents a partial MRP transaction report for the parts and necessary to manufacture the lamp shown in the product structure to the right complete the transaction report in the exhibit for the parks and answer the following questions

Complete the MRP transaction report in the exhibit for the parts and then answer the following questions

Lamp: Leadtime = 1 day Lot for Lot Saftey stock=0

1 2 3 4 5 6 7 8 9
Gross Requirements 65 60 40
Scheduled receipts 20
On Hand 28
Planned order release