Question: Expected Project duration? Determine Critical path. The probability that the project will be completed in 50 weeks? Activity B D Crash Time 3 8 6
Expected Project duration?
Determine Critical path.
The probability that the project will be completed in 50 weeks?


Activity B D Crash Time 3 8 6 8 7 9 Crash Cost $ 35,200 $ 95,625 $ 50,400 $ 224,800 $ 394,000 $ 196,250 23 - IOOOO Optimistic Most Likely Pessimistic Normal Time Time Time Cost 2 4 $ 28,000 7 10 14 $ 81,000 7 8 9 $ 40,000 16 18 $ 160,000 12 16 30 $ 274,000 10 14 18 $ 145,000 1 2 3 $ 11,000 3 4 6 $ 42,000 1 1 1 $ 8,000 4 6 7 $ 59,000 1 1 1 $ 5,000 8 12 14 $ 136,000 9 12 20 $ 87,000 1 1 1 $ 10,000 2 $ 62,800 5 $ 64,125 6 6 $ 221,000 $ 143,375 EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATIONAFTER ARCHITECTURAL DESIGN AND PLANT LAYOUT COMPLETED Activity Immediate Predecessor A B C D E F G H I J K L M N O Description Finalize lease Obtain permits Zoning approval Electrical and pneumatic construction Quality/supervisor pod construction Anodizing line installation Machine shop equipment removal and reinstallation Climate controlled proving room construction Assembly relocation Paint line relocation Auxiliary equipment Office construction Information technology services Office move Project end A B, C B, C B, C DF E G I J E E L, M H, K, N Estimated Time (Weeks) 4 10 8 16 16 14 2 4 1 6 1 12 12 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
