Question: Expected Project duration? Determine Critical path. Probability that the project will be completed in 50 weeks? EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATIONAFTER ARCHITECTURAL DESIGN

Expected Project duration? Determine Critical

Expected Project duration?

Determine Critical path.

Probability that the project will be completed in 50 weeks?

EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATIONAFTER ARCHITECTURAL DESIGN AND PLANT LAYOUT COMPLETED Activity Description Immediate Predecessor A B C D E F G H Finalize lease Obtain permits Zoning approval Electrical and pneumatic construction Quality/supervisor pod construction Anodizing line installation Machine shop equipment removal and reinstallation Climate controlled proving room construction Assembly relocation Paint line relocation Auxiliary equipment Office construction Information technology services Office move Project end B,C B, C B, C DF E G 1 J E E LM H, KN Estimated Time (Weeks) 4 10 8 16 16 14 2 4 1 6 1 12 12 1 J L M N 0 EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATIONAFTER ARCHITECTURAL DESIGN AND PLANT LAYOUT COMPLETED Activity Description Immediate Predecessor A B C D E F G H Finalize lease Obtain permits Zoning approval Electrical and pneumatic construction Quality/supervisor pod construction Anodizing line installation Machine shop equipment removal and reinstallation Climate controlled proving room construction Assembly relocation Paint line relocation Auxiliary equipment Office construction Information technology services Office move Project end B,C B, C B, C DF E G 1 J E E LM H, KN Estimated Time (Weeks) 4 10 8 16 16 14 2 4 1 6 1 12 12 1 J L M N 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!