Question: Expected Project duration? Determine Critical path. Probability that the project will be completed in 50 weeks? EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATIONAFTER ARCHITECTURAL DESIGN

Expected Project duration?
Determine Critical path.
Probability that the project will be completed in 50 weeks?
EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATIONAFTER ARCHITECTURAL DESIGN AND PLANT LAYOUT COMPLETED Activity Description Immediate Predecessor A B C D E F G H Finalize lease Obtain permits Zoning approval Electrical and pneumatic construction Quality/supervisor pod construction Anodizing line installation Machine shop equipment removal and reinstallation Climate controlled proving room construction Assembly relocation Paint line relocation Auxiliary equipment Office construction Information technology services Office move Project end B,C B, C B, C DF E G 1 J E E LM H, KN Estimated Time (Weeks) 4 10 8 16 16 14 2 4 1 6 1 12 12 1 J L M N 0 EXHIBIT 1: ACTIVITIES TO COMPLETE PLANT RELOCATIONAFTER ARCHITECTURAL DESIGN AND PLANT LAYOUT COMPLETED Activity Description Immediate Predecessor A B C D E F G H Finalize lease Obtain permits Zoning approval Electrical and pneumatic construction Quality/supervisor pod construction Anodizing line installation Machine shop equipment removal and reinstallation Climate controlled proving room construction Assembly relocation Paint line relocation Auxiliary equipment Office construction Information technology services Office move Project end B,C B, C B, C DF E G 1 J E E LM H, KN Estimated Time (Weeks) 4 10 8 16 16 14 2 4 1 6 1 12 12 1 J L M N 0Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts