Question: Expected time Assignment: Using the provided data on task durations with optimistic, most probable, and pessimistic estimates, determine the network diagram, critical path and expected
Expected time Assignment:
Using the provided data on task durations with optimistic, most probable, and pessimistic
estimates, determine the network diagram, critical path and expected time.
Activity Dependency
Optimistic
Duration
days
Most Probable
Duration
days
Pessimistic
Duration days
A
B A
C B
D B
E C
F D
G E F