Question: Expected time Assignment: Using the provided data on task durations with optimistic, most probable, and pessimistic estimates, determine the network diagram, critical path and expected

Expected time Assignment:
Using the provided data on task durations with optimistic, most probable, and pessimistic estimates, determine the network diagram, critical path and expected time.
\table[[,Dependency,\table[[Optimistic],[Duration],[(days)]],\table[[Most Probable],[Duration],[(days)]],\table[[Pessimistic],[Duration (days)]]],[Activity,-,4,6,8],[A,A,7,9,12],[C,B,10,12,16],[D,B,6,8,10],[E,C,5,7,9],[F,D,9,13,16],[G,E, F,2,4,6]]
 Expected time Assignment: Using the provided data on task durations with