Question: Expected Value Method You have a project to build an Automated Driving Assist System (ADAS). The ADAS has four modules; Pedestrian Detection, road-sign detection, traffic
Expected Value Method
You have a project to build an Automated Driving Assist System (ADAS). The ADAS has four modules; Pedestrian Detection, road-sign detection, traffic lane identification and Vehicle proximity detection. Each module is to take one month to build and 1000 has been budged per module. The modules are planned to be completed one after the other. Today is the end of month 3.
| Module | Month 1 | Month 2 | Month 1 | Month 4 | Status at the end of month 3 |
| Pedestrian Detection | S-----F | Complete, spent 1000$ | |||
| Road-Sign Detection | S----PF | -----F | Complete, Spent 1200$ | ||
| Traffic Lane Identification | Ps----S----PF | 50% done, spent 600$ | |||
| Vehicle Proximity detection | PS-----PF | not yet started |
Key: S= Actual Start. F=Actual Finish, PS= Planned start, PF= Planned finish
Use the above project status chart and calculate the measures given in the table below.
| What is | Calculation | Answer | Interpretation of Answer | |
| 1 | PV | |||
| 2 | EV | |||
| 3 | AC | |||
| 4 | Cost variance (CV) | |||
| 5 | CPI | |||
| 6 | Schedule Variance(SV) | |||
| 7 | SPI | |||
| 8 | EAC | |||
| 9 | ETC | |||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
