Question: Expected Value Method Practice Problem You have a project to build an Automated Driving Assist System ( ADAS ) . The ADAS has four modules;
Expected Value Method
Practice Problem
You have a project to build an Automated Driving Assist System ADAS The ADAS has four modules; Pedestrian Detection, roadsign detection, traffic lane identification and Vehicle proximity detection. Each module is to take one month to build and has been budged per module. The modules are planned to be completed one after the other. Today is the end of month
tableModuleMonth Month Month Month tableStatus atend ofMonth tablePedestrianDetectionSFtableCompletespent StableRoadsigndetectionSPFtableCompletespent StableTraffic laneidentificationPSSPFtable done,spent $tableVehicleproximitydetectionPSPFtableNot yetstarted
Key Actual Start, Actual Finish, Planned Start, and Planned Finish
Use the above project status chart and calculate the measures given in the table below.
tableWhat isCalculation,Answer,Interpretation of AnswerPVEVACCost Variance CVCPI,,,Schedule Variance SVSPI,,,EAC,,,ETC,,,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock