Question: Explain in detail this 3 problem occur in multiproject enviroment. 1. Overall schedule slippage Shared resources causes a ripple effectdelays in one project create delays
1. Overall schedule slippage
Shared resources causes a ripple effectdelays in one project create delays for other projects.
2.Inefficient resource utilization
Different schedules and requirements by multiple projects create the peaks and valleys in overall resource demands.
3.Resource bottlenecks
Shortages of critical resources required by multiple projects cause delays and schedule