Question: Exponential smoothing with = 0.30; use 40 for week 2 forecast. Assignment 3 (Chapter 3) This assignment consists of two questions. Question 1: This question

Exponential smoothing with = 0.30; use 40 for Exponential smoothing with = 0.30; use 40 for week 2 forecast.

Assignment 3 (Chapter 3) This assignment consists of two questions. Question 1: This question is worth 10 points A contractor's records during the least five weeks indicate the number of job requests: Week 2 3 4 Request 40 44 55 48 1 5 72 Predict the number of requests for week 4 week 5, week 6 using each of the following methods