Question: EXTRA CREDIT 3 - Precedence Diagram: | 4. Draw the precedence diagram and compute the early start, early finish, late start, late finish, total float,

EXTRA CREDIT 3 - Precedence Diagram: | 4. Draw the precedence diagram and compute the early start, early finish, late start, late finish, total float, and free float for the project whose relationships are given below. Eliminate all redundant logic. Identify and indicate the critical path, THE DATA BELOW IS FOR ONE PROJECT ONLY. Activity Duration Predecessors Activity Duration Predecessors A 4 B. D M 3 P.W.Z B 8 F N L 4 ADF P 3 SU 6 F 10 N.L AD 4 R.LD L B.C.E 8 N.R. T G.K U DE.R X 12 L 4 EL.X