Question: Construct an activity diagram using Table 3b below. Activity Immediate Predecessor Duration (weeks) A - 4 B A 6 C A 4 D B 6

  1. Construct an activity diagram using Table 3b below.

Activity

Immediate Predecessor

Duration (weeks)

A

-

4

B

A

6

C

A

4

D

B

6

E

C

3

F

C

3

G

D, E

5

H

F, G

4

Table 3b: Activity Duration and Relationship for a steel fabrication project

For each activity, show the computed values of early start, early finish, late start, late finish, total float, free float and the Critical Path.