Question: Construct an activity diagram using Table 3b below. Activity Immediate Predecessor Duration (weeks) A - 4 B A 6 C A 4 D B 6
- Construct an activity diagram using Table 3b below.
| Activity | Immediate Predecessor | Duration (weeks) |
| A | - | 4 |
| B | A | 6 |
| C | A | 4 |
| D | B | 6 |
| E | C | 3 |
| F | C | 3 |
| G | D, E | 5 |
| H | F, G | 4 |
Table 3b: Activity Duration and Relationship for a steel fabrication project
For each activity, show the computed values of early start, early finish, late start, late finish, total float, free float and the Critical Path.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts