Question:
Transcribed Image Text:
F < D 3 B 7 A 6 8 G 5 C 11 E H 6 4 6 Use the network diagram and activity lengths in the nodes to determine ? the early start time for activity D. > F < D 3 B 7 A 6 8 G 5 C 11 E H 6 4 6 Use the network diagram and activity lengths in the nodes to determine ? the early start time for activity D. >