Question: F H D E F G Q2 (10 points) The expected time of a project is 20 days. The variance of the project is 3.88

F H D E F G Q2 (10 points) The expected time of a
F H D E F G Q2 (10 points) The expected time of a project is 20 days. The variance of the project is 3.88 a. What is the probability of finishing the project in 23 days? b. What is the probability that the project will take more than 22 days? c. What is the probability of finishing the project in 20 days