Question: In the project described below, consider only the path ACGH. 1- Compute the expected task time and variance. 2- What is the expected path time

In the project described below, consider only the path ACGH.

1- Compute the expected task time and variance.

2- What is the expected path time for ACGH?

3- What is the path standard deviation for ACGH?

4- What is the probability that this path will be completed by day 95?

In the project described below, consider only the

OO Problem Set5 Qu Search Sheet Home Insert Page Layout Formulas Data Review View 3+ Share Arial 10 A- A- Eto Wrap Text Ceneral Insert - Ex Delete - KA 49 Paste I B .no A A Merge & Center & $ . % .00 Conditional Format Formatting us Table Cell Styles Format Sort Filter D28 X fx E F H 1 J K L M N N 0 expected time o? (variance) A B D 1 In the project described below, consider only the path ACGH. 2 3 Compute the expected task time and variance. 4 5 optimistic most likely pessimistic 8 Task time time time 7 A 20 20 20 3 3 6 15 9 25 32 39 10 10 D 20 30 40 11 E 12 15 22 12 F 7 9 22 13 G 15 20 24 14 H 14 19 27 15 " 16 17 What is the expected path time for ACGH? 18 19 What is the path standard deviation for ACGH? 20 21 What is the probability that this path will be completed by day 95? 22 23 24 25 26 27 28 Summary V2 #4 41 3 H5 + Reach | C 130%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!