Question: F M , F P , S M , S P , T M , T P 0 A linear programming computer package is needed.

FM,FP,SM,SP,TM,TP0 A linear programming computer package is needed.
number of straps purchased. Express time in minutes per unit.)
Min 39FM+52FP+12.5SM+16SP+7.5TM+8.5TP
Cutting constraint 3.5FM+1.3SM+0.8TM21000
Milling constraint
Shaping constraint 3.1FM+2.6SM+1.7TM40800
Frame constraint FM+FP=4,500
Support constraint SM+SP=9000
Strap constraint TM+TP=4,500
FM,FP,SM,SP,TM,TP0
How many of each component should be manufactured and how many should be purchased? (Round your answers to the nearest whole number.)
How many of each component should be manufactured and how many should be purchased? (Round your answers to the nearest whole number.)
(b) What is the total cost (in $ ) of the manufacturing and purchasing plan?
$321750
(c) How many hours of production time are used in each department? (Round your answers to two decimal places.)
(d) How much (in $ ) should Frandec be willing to pay for an additional hour of time in the shaping department?
$
(e) Another manufacturer has offered to sell frames to Frandec for $45 each. Could Frandec improve its position by pursuing this opportunity? Why or why not? (Round your answer to three decimal places.)
-- Select -cdots. The reduced cost of indicates that the solution -- Select - be improved.
Need Help?
 FM,FP,SM,SP,TM,TP0 A linear programming computer package is needed. number of straps

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!