Question: f) Using the standard normal table, the probability that hopkins hospitality will finish the project in 42 weeks or less is ____ a) The expecied

f) Using the standard normal table, the probability that hopkins hospitality will finish the project in 42 weeks or less is ____
f) Using the standard normal table, the
a) The expecied (entmatad) time for activity C is weoks. (Round your response to two decima places) b) The variance for activity C is 2.8 weeks (Round your response to fwo decimad places ) c) Based on the calculation of the estimated times, the citical path is ACFH=JK d) The estimated time for the critical path is weeks. (Round your nesponse to hoo decimal places) e) The activity variance along the critical path is weeks. (Round yout responso to two docimal ploces) f) Ueing the standard neemal table, the probabilty that Hopkins Hospitality will frish the project in 42 weoks or less is (Enter as a probabity and round yeur rouponse to Invee decinta piaces)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!