Question: Facility A B # Generators 2 0 4 2 Fixed Cost $ 2 2 , 5 0 0 $ 3 5 , 0 0 0

Facility
A B
# Generators 2042
Fixed Cost $22,500 $35,000
Var. Cost $1,300.00 $950.00 c. Jenny Power Source Solutions Chief Procurement Officer (CPO) received a late bid from Facility C. If Facility C has a fixed cost of $40,000 and a variable cost of $800.00 per unit, what should Jenny Power Source Solutions? [Blank3]{Hint: Calculate the crossover point between A and B, B and C and, A and C, to find which facility would be the best}