Question: AON network diagram: B C E Normal Cost ($) 500 600 800 1,500 1,750 1,200 1,500 500 G D Normal Crash Time Time Activity (weeks)

AON network diagram: B C E Normal Cost ($) 500

AON network diagram: B C E Normal Cost ($) 500 600 800 1,500 1,750 1,200 1,500 500 G D Normal Crash Time Time Activity (weeks) (weeks) A 3 2 B 4 3 5 3 D 5 4 E 6 4 F 5 5 G 9 5 H 3 3 Using the information given, (a) Calculate the completion time for this project. Project completion time = (b) Identify the activities on the critical path. Critical activities: H Crash Cost ($) 900 700 1,300 2,150 2,250 1,200 2,100 500 weeks. Maximum weeks Reduced 1 1 2 1 2 0 4 0 Crash Cost per Week ($) 400 100 166.67 325 250 0 150 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!