Question: Factory Basics Consider a 3-workstation production line with a single product that must be processed through station sequence 1-2-3. The following data are pertinent: Workstation
Factory Basics
Consider a 3-workstation production line with a single product that must be processed through station sequence 1-2-3. The following data are pertinent:
| Workstation | Identical Machines | Average processing time Minutes/job |
| 1 | 7 | 14 |
| 2 | 10 | 25 |
| 3 | 2 | 3 |
(a) Identify all parameters and list them with their respective values.
b.What are the bottleneck rate , the raw process time, , and the critical WIP ?
c.Compare the average cycle time when the WIP level is set at 20 jobs, under the assumptions of the best case, the worst case and the practical worst case.