Question: FCFS JOB PROCESSING TIME DUE TIME FLOW TIME LATENESS A 20 50 0 + 20 = 20 B 30 70 20 + 30 = 50
FCFS JOB PROCESSING TIME DUE TIME FLOW TIME LATENESS A 20 50 0 + 20 = 20 B 30 70 20 + 30 = 50 C 10 45 50 + 10 = 60 15 D 16 100 60 + 16 = 76 E 18 80 76 + 18 = 94 14 AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 29 / 5 = 5.8 UTILIZATION METRIC = (TOTAL PROCESSING TIME / TOTAL FLOW TIME) * 100 = 94 / 300 * 100 = 31.33 EDD JOB PROCESSING TIME DUE TIME FLOW TIME LATENESS C 10 45 0 + 10 = 10 A 20 50 10 + 20 = 30 B 30 70 30 + 30 = 60 E 18 80 60 + 18 = 78 D 16 100 78 + 16 = 94 AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 0 / 5 = 0 UTILIZATION METRIC = (TOTAL PROCESSING TIME / TOTAL FLOW TIME) * 100 = 94 / 272 * 100 = 34.56 LPT JOB Processing Time (days) Due Date Flow Time Job Lateness B 30 70 0 + 30 = 30 A 20 50 30 + 20 = 50 0 E 18 80 50 + 18 = 68 D 16 100 68 + 16 = 84 C 10 45 84 + 10 = 94 49 AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 49 / 5 = 9.8 UTILIZATION METRIC = (TOTAL PROCESSING TIME / TOTAL FLOW TIME) * 100 = 94 / 326 * 100 = 28.83 2.
If job lateness is the selection criteria which is the best rule (10 marks)
Which is the best rule if Ramsons is concerned about utilization (10 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts