Question: Ifthe indirect costs for each duration are $520 for 27 ueeks, $460 for 26 weeks, $400 for 25 weeks, $340 for 24 weeks, $280


Ifthe indirect costs for each duration are $520 for 27 ueeks, $460 for 26 weeks, $400 for 25 weeks, $340 for 24 weeks, $280 for 23 vseeks, and $240 for 22 weeks, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $30 for every week you shorten the project from your original planning network. Would you take it? If so, for how many weeks? (8+2+2=12 M) ACT. NORMAL NORMAL CASH A c T'ME to 6 cosr CRASH COST TIME go 50 too t 2 too
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
