Question: If the indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks, $180 for 25 weeks, $120 for 24 weeks, $60
If the indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks, $180 for 25 weeks, $120 for 24 weeks, $60 for 23 weeks, and $50 for 22 weeks, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every week you shorten the project from your original network. Would you take it? If so for how manyweeks?
.png)
Normal Cost Nomal Time Maximum Crash Time Crash Cost (Slope) 10 10 15 100 Time unit 1 week Project duration Total direct cost $ Project duration Total direct cost Activities changed
Step by Step Solution
3.64 Rating (169 Votes )
There are 3 Steps involved in it
The duration for this schedule is weeks It should be reminded that they crash the schedul... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
177-B-M-L-P-M (1420).docx
120 KBs Word File