Question: If the indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks, $180 for 25 weeks, $120 for 24 weeks, $60

If the indirect costs for each duration are $300 for 27 weeks, $240 for 26 weeks, $180 for 25 weeks, $120 for 24 weeks, $60 for 23 weeks, and $50 for 22 weeks, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every week you shorten the project from your original network. Would you take it? If so for how manyweeks?

If the indirect costs for each duration are $300 for

Normal Cost Nomal Time Maximum Crash Time Crash Cost (Slope) 10 10 15 100 Time unit 1 week Project duration Total direct cost $ Project duration Total direct cost Activities changed

Step by Step Solution

3.64 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The duration for this schedule is weeks It should be reminded that they crash the schedul... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

177-B-M-L-P-M (1420).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!