Question: Figure 1 1 . 8 is the network for the Largesse Hydro Project: Figure 1 1 . 8 Largesse Hydro Project. The following table gives

Figure 11.8 is the network for the Largesse Hydro Project:
Figure 11.8
Largesse Hydro Project.
The following table gives the baseline cost and time estimates (BCE and BTE), the cost and time estimates to correct for failure, and the likelihood of failure for each work package.
\table[[WBS Elerment,BCE,Corrective],[BTE (wk),Cost,Ttime,Likelihood],[L,$20.000,9,$4,000,2,2],[V,$16,000,8,$4,000,2,.3],[T,$32,000,5,$8,000,2,.1],[U,$20.000,7,$12,000,3,2],[S,$16,000,3,$4,000,1,3],[J,$18,000,3,$4,000,1,.1],[R,$10,000,4,$4,000,3,.3],[C,$15,000,6,$5,000,2,3]]
a. Determine the risk time and risk cost for all the WBS elements of the project.
b. Consider the risk times on noncritical paths. Which activities and paths should be watched carefully as posing the highest risks?
c. What is the project expected cost (EC) and expected time (ET)?
 Figure 11.8 is the network for the Largesse Hydro Project: Figure

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!