Question: The activity network for the Largesse Hydro Project is shown below: The following table gives the baseline cost estimate ( BCE ) and baseline time
The activity network for the Largesse Hydro Project is shown below:
The following table gives the baseline cost estimate BCE and baseline time estimates BTE
the cost and time estimates to correct for failure, and the likelihood of failure for each work
package or WBS element:
a Determine the risk time and risk cost for all the WBS elements of the project.
b What is the project's expected cost EC and expected time ET