Question: FIGURE 1 7 . 3 Gantt chart for bank example For the bank project, crash the project by reducing the duration of the project from

FIGURE 17.3
Gantt chart for bank example
For the bank project, "crash" the project by reducing the duration of the project from 20 weeks ( which was the example in the textbook and during class) down to 18 weeks. Perform the forward pass, backward pass, calculate the slacks for each activity and identify the critical path(s).