Question: Figure 2 : Activity - on - node legend system 3 . 2 . Identify the critical path. 3 . 3 . Identify the activities

Figure 2: Activity-on-node legend system
3.2. Identify the critical path.
3.3. Identify the activities with slack.
3.4. Identify two activities in a mandatory dependency relationship. Explain what a mandatory
dependency is and why the identified activities have a mandatory dependency.