Question: Figure 5 . 4 1 6 ) Use the information in Figure 5 . 4 . What are the required predecessors of activity H ?

Figure 5.4
16) Use the information in Figure 5.4. What are the required predecessors of activity H?
A) E & G
B) A through F, including E
C) Activity H has no required predecessors.
D) D
Answer: A
17) Use the information in Figure 5.4. If each task has a work time of one minute, what is the theoretical minimum cycle time?
A) There is no minimum cycle time.
B)1 minute
C)8 minutes
D) The cycle time cannot be determined with the information given.
Answer: B
18) Use the information in Figure 5.4. If each task has a work time of one minute and there are 480 work minutes in a day, what is the task assignment at the fourth workstation if maximum output is desired?
A) A
B) B
C) C
D) D
Answer: D
19) Use the information in Figure 5.4. If each task has a work time of one minute and there are 8 hours in a day, what is the task assignment at the first station if 160 units should be produced each day?
A) A, B, C, D
B) H, G, F, E
C) A, B, C
D) H, G, F
Answer: C
20) Use the information in Figure 5.4. If each task has a work time of one minute and there are 8 hours in a day, what is the minimum number of stations if 240 units should be produced each day?
A) one
B) two
C) three
D) four
Answer: D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!