Question: Please also USE table below OVERVIEW Before staring the construction, we should assign resources (e.g., people, equipment, and material) to each activity. In this assignment,

Please also USE table below OVERVIEW Before

Please also USE table below

Please also USE table below OVERVIEW Before

OVERVIEW Before staring the construction, we should assign resources (e.g., people, equipment, and material) to each activity. In this assignment, we will focus on carpenters which is one of the critical resources in reinforcement concrete structure work. The below table shows carpenters needed for each project. You can create your resource diagrams using any method that you want to. You will need to create a digital version of the diagrams to upload to the course. ACTIVITY ID DURATION PREDECESSORS CARPENTERS ACTIVITY NAME Move in 1 3 2 Excavate 1 3 Backfill 18 4 2 5 4 1 6 Drive pile abutment #1 Form & Rebar footing #1 Concrete footing #1 Strip footing #1 Form & Rebar abutment #1 5 7 6 3 days 5 days 7 days 3 days 2 days 1 day 1 day 4 days 2 days 3 days 3 days 3 days 2 days 1 day 8 7 3 9 Concrete abutment #1 8 2 10 Strip abutment #1 9 3 11 Rub concrete abutment #1 10 12 Drive pile abutment #2 4 13 Form & Rebar footing #2 7,12 14 13 1 15 Concrete footing #2 Strip footing #2 Form & Rebar abutment #2 14 16 10,15 3 17 Concrete abutment #2 16 2 18 17 Strip abutment #2 Rub concrete abutment #2 19 1 day 4 days 2 days 3 days 3 days 2 days 4 days 3 days 10 days 18 20 Set girder 18 21 Deck form and rebar 20 22 Deck concrete 3,21 3 23 Deck strip & finish 22,11,19 Please answer the following questions. 1) (30 points) Draw a resource diagram for the carpenters. 2) (70 points) Assume that we can hire a maximum of three carpenters. Please perform the limited resource leveling and update the schedule. You can use the table attached below to do so: Activity Name Duration ESD EFD LSD LFD Total Float Free Float Critical Activity Move in 3 Excavate 5 Backfill 7 3 Drive pile abutment #1 Form & Rebar footing #1 2 Concrete footing #1 1 Strip footing #1 1 4 Form & Rebar abutment #1 Concrete abutment #1 2 Strip abutment #1 3 3 Rub concrete abutment #1 Drive pile abutment #2 Form & Rebar footing #2 3 2 Concrete footing #2 1 Strip footing #2 1 4 Form & Rebar abutment #2 Concrete abutment #2 2 Strip abutment #2 3 Rub concrete abutment #2 3 Set girder 2 Deck form and rebar 4 Deck concrete 3 Deck strip & finish 10 Total Duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!