Question: Figure 7 - 2 Research Project Consider the Research Project depicted in Figure 7 - 2 . Based on the information provided, which activity can

Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2. Based on the information provided, which activity can you delay by one day without impacting the expected completion date for the project?
a. Activity A
b. Activity C
c. Activity D
d. Activity B