Question: Figure 7 - 2 Research Project Consider the Research Project depicted in Figure 7 - 2 . Based on the information provided, what is the

Figure 7-2 Research Project
Consider the Research Project depicted in Figure 7-2. Based on the information provided, what is the slack associated with activity C - "Review Reports"?
Question 20Select one:
a.
0 days
b.
1 day
c.
2 days
d.
4 day